Prentice Village Infrastructure Projects: Full Coverage & Timeline

Quick Summary

Prentice Village Infrastructure Projects is an ongoing municipal government story in Price County, Wisconsin
(Prentice Village)
, first tracked on August 01, 2026
and last updated June 08, 2026
.

Timeline of Events

February 09, 2026 — Village of Prentice Board

Railroad St. water main project: 8 bids, lowest JGJ Dirt LLC $699,813.62, 60-day completion.

April 09, 2026 — Village of Prentice Board

Apple/Ash Streets: repeated water main breaks, sewer issues. Approved Ayres proposal, pursuing Safe Drinking Water/Clean Water funding.

June 08, 2026 — Village of Prentice Board

Street project started, completion expected first part of August.

Meetings to Watch

This story may surface in the following regular meetings:

  • Village of Prentice Board

Related Sagas

Tracked keywords: water main, apple street, ash street, railroad street, sewer, street project, ayres

Last updated: August 10, 2026